I wanted to open discussion about the system of not putting sheathing on walls when you're building them and get a wall sheathing crew in to do it at a later date. I know there's many of the NJ pros here that say they have sheathing crews come by and blast it out.
I'm getting ready to start one with the Zip System and am considering this. I have some concerns but mostly because I've never done it this way. I'm assuming you have no troubles with bracing as your building goes up but wonder if you have any precautions to bring forth that I may not see. Some people use the adjustable braces which I have no desire buying a bunch of right now. Also, does the crew come after the 2nd floor walls are done and prior to any roof framing? Is there any way to describe in man hours how long it takes. I would assume once you get going and get your system it will fly. Real curious about this and tempted.
__________________
If you correct your mind, the rest of your life will fall into place ~Lao Tzu Custom Cabinetry - Portland, Cape Elizabeth, Scarborough, Kennebunkport, Yarmouth, Falmouth, Cumberland, Ogunquit, Maine Salmon Falls Cabinetry Last edited by KentWhitten; 11-11-2009 at 12:33 PM. |
|
|
|
|
|
#2 | |
|
Pro
Trade: Framing Contractor
Join Date: Jun 2004
Location: Caldwell, New Jersey
Posts: 1,541
|
Re: Non Sheathed MethodQuote:
You will be amazed how fast the sheathing crews are. They fly up the walls and fly ion the roof, you can't beat them, they have their own system and it works I nail a 2x4 brace on the outside corner of the wall so that when you stand the wall up and nail the corner post in you can shoot the temp brace in plumbing the wall up. After the two outside corners are plumb I throw a temp brace in the middle of the wall between the plates where the interior perpendicular walls go. That will hold the wall in place. As the rest of the outside walls are being framed someone is toenailing the bottoms of the studs into the shoe. Same steps for the outside walls.After all outside walls are up the interior walls get framed and the top plate overlaps the outside walls and get nailed, that locks everything into place. After every single wall is up I string the outside walls placing a piece of 5/4 on the outside corners and just wrap a mason line around the entire four walls. Takes 5 minutes. A 16' piece of 5/4 gets nailed to the inside of all outside corners of the exterior walls. Plumb all 4 corners and nail braces. Now the outside corners are done.Now I use 12' 2x4's nailed along side the stud underneath the bottom of the first top plate maybe one or two in each room depending on what size the room is because the perpendicular wall is also used as a brace for the outside walls. These braces push or pull the outside walls straight to the mason line. Once every wall is pushed in or out to the mason line and all braces are nailed, that's all you need. You frame the entire house rafters and all and then the sheathing crew comes in. After they are done you can remove the braces. The braces get used for packing out rakes and the 2x4's get used for collar ties and any miscellaneous framing. Will you be facenailing the studs and then lifting up the walls?
__________________
Joe Carola |
|
|
|
|
| The Following User Says Thank You to Joe Carola For This Useful Post: | wallmaxx (11-11-2009) |
|
|
#3 |
|
KemoSabe
Trade: residential framing/siding/general carpentry
Join Date: Feb 2009
Location: Vineland, New Jersey
Posts: 12,823
|
Re: Non Sheathed Method
Framerman, now your talking my language. I never sheath walls on the floor. Aside from box nailing my walls together, I do pretty much the same as Joe. The only difference is, I like to sheath the walls before I move on to roof framing. I have done a few buildings complete with no sheathing, but I get leary with this method along the coast. Too much risk of wind working the braces. I have seen a few buildings come down because the framers sheathed the roof before the walls, so I don't recommend that method ever.
If you hire in a crew, double check their nailing before they get paid and let them know what you expect in advance.On average, two men and myself ran about 100 sheets a day on a building that was 7 rows high 56' long. Setup with pumpjacks takes a couple hours, but I leave them up for papering and window installation, as well as siding if it's in my contract. Sheathing crews are much faster, but I'm not into sheathing 3 stories off of extension ladders, nor for $5 a sheet. They probably won't make much effort to straighten bowed studs either.
__________________
__________________________________ "Walking the fine line between production and perfection" __________________________________ |
|
|
|
|
|
#4 |
|
Pro
Trade: siding
Join Date: Mar 2007
Location: west milford n.j.
Posts: 8,857
|
Re: Non Sheathed Method
it seems like there is some detail that has to be paid as far as the zip tape system goes,not rocket science but it needs to be installed and rolled correctly for it to do its job. jmo
__________________
Tom |
|
|
|
|
|
#5 | |
|
KemoSabe
Trade: residential framing/siding/general carpentry
Join Date: Feb 2009
Location: Vineland, New Jersey
Posts: 12,823
|
Re: Non Sheathed MethodQuote:
__________________
__________________________________ "Walking the fine line between production and perfection" __________________________________ |
|
|
|
|
|
|
#6 |
|
Pro
Trade: siding
Join Date: Mar 2007
Location: west milford n.j.
Posts: 8,857
|
Re: Non Sheathed Method
they actually have a tape dispenser with a built in roller,also a big j roller with a specially textured head
__________________
Tom |
|
|
|
|
|
#7 | |
|
KemoSabe
Trade: residential framing/siding/general carpentry
Join Date: Feb 2009
Location: Vineland, New Jersey
Posts: 12,823
|
Re: Non Sheathed MethodQuote:
Guess I should've done my homework on that one.
__________________
__________________________________ "Walking the fine line between production and perfection" __________________________________ |
|
|
|
|
|
|
#8 |
|
Pro
Trade: GC/Remodeling
Join Date: Sep 2007
Location: Central America (Kansas)
Posts: 1,923
|
Re: Non Sheathed Method
sounds like Joe's got it..
I like a 12 or 16 2x diagonal brace shoved up into the top of the outside corners(inside). Nailed into both the top and bottom plates, makes the corners solid till sheathing.. Then you can nail any wonky studs to the brace to hold them straight till sheathed.
__________________
-Steve "The most beautiful thing we can experience is the mysterious. It is the source of all true art and science." ~ Albert Einstein |
|
|
|
|
|
#9 |
|
Pro
Trade: siding
Join Date: Mar 2007
Location: west milford n.j.
Posts: 8,857
|
Re: Non Sheathed Method
was at a rough framing Road show today
__________________
Tom |
|
|
|
|
|
#10 | |
|
Pro
Trade: Framer
Join Date: Mar 2006
Location: Port Orchard, WA
Posts: 711
|
Re: Non Sheathed MethodQuote:
That's it. |
|
|
|
|
| The Following User Says Thank You to Timuhler For This Useful Post: | Tom Struble (11-11-2009) |
|
|
#11 |
|
Pro
Trade: Framing
Join Date: May 2009
Location: SI, NY
Posts: 506
|
Re: Non Sheathed Method
it's faster.
i rarely do it for several reasons. one, just like loneframer i like to sheath walls before the roof goes on. partly because the box doesn't move so much, partly because i like the ply to go all the way up to the top of plate and be nailed there. two, sheathing crews are pretty rough. most of my work gets scrutinized, and i don't like people saying i do shoddy work. i'll do shoddy work if it isn't going to be scrutinized though
|
|
|
|
|
|
#12 | |
|
KemoSabe
Trade: residential framing/siding/general carpentry
Join Date: Feb 2009
Location: Vineland, New Jersey
Posts: 12,823
|
Re: Non Sheathed MethodQuote:
Sheathing the walls before framing the roof to stiffen the structure just makes good sense in this scenario.
__________________
__________________________________ "Walking the fine line between production and perfection" __________________________________ |
|
|
|
|
|
|
#13 |
|
Pro
Trade: siding
Join Date: Mar 2007
Location: west milford n.j.
Posts: 8,857
|
Re: Non Sheathed Method
[quote=ClemS;805480]go all the way up to the top of plate and be nailed there
thats fire blocking code here,i had an inspector make me put in 4''rips of ply before i could do the soffit i was just the sider
__________________
Tom Last edited by Tom Struble; 11-11-2009 at 08:06 PM. |
|
|
|
|
|
#14 |
|
Pro
Trade: Framing,Remodeling,General Contractor
Join Date: Mar 2009
Location: Kansas City
Posts: 1,922
|
Re: Non Sheathed Method
What is this sheeting crew you speak of? Is it a bunch of Mexicans?
|
|
|
|
|
|
#15 |
|
Pro
Trade: Framing
Join Date: May 2009
Location: SI, NY
Posts: 506
|
Re: Non Sheathed Method
[quote=tomstruble;805510]don't know about fire blocking, but it's definitely better for shear. some guys who use sheathers will run a 2' ribbon around the top of the box and let the sheather go up to it (tried it, and doesn't always come out looking too crisp)
|
|
|
|
|
|
#16 |
|
Pro
Trade: Framing
Join Date: May 2009
Location: SI, NY
Posts: 506
|
Re: Non Sheathed Method |
|
|
|
|
|
#17 |
|
Pro
Trade: Framing,Remodeling,General Contractor
Join Date: Mar 2009
Location: Kansas City
Posts: 1,922
|
Re: Non Sheathed Method
How hard is it to put sheeting on a wall when it is laying on the deck?
|
|
|
|
|
|
#18 |
|
Pro
Trade: siding
Join Date: Mar 2007
Location: west milford n.j.
Posts: 8,857
|
Re: Non Sheathed Method
inspector ''explained'' to me a fire in the wall could pass the gap in the sheathing and then to the roof
i didn't frame it but i did what he asked to keep my job moving cutting the plumb cut on the birdsmouth back 1/2'' on a hundred or so rafters was fun
__________________
Tom |
|
|
|
|
|
#19 | |
|
Pro
Trade: Framing
Join Date: May 2009
Location: SI, NY
Posts: 506
|
Re: Non Sheathed MethodQuote:
framing crews around here are also pretty slim, 2-3 guys. part of the reason why all this hurricane strapping non-sense is so rampant now is because people don't lap the box with their sheathing. |
|
|
|
|
|
|
#20 |
|
Pro
Trade: Framing
Join Date: May 2009
Location: SI, NY
Posts: 506
|
Re: Non Sheathed Method
in some situations i will fly the birdsmouth out 3/4" and space my rafters and sheathe after the roof is on. mostly on roof raises though, because the quicker your ridge is up, the better the tarp job at the end of the day.
|
|
|
|
| The Following User Says Thank You to ClemS For This Useful Post: | Tom Struble (11-15-2009) |
![]() |
| Thread Tools | Search this Thread |
| Display Modes | Rate This Thread |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Framing method for windows in existing steel stud inerior wall. | ridge runner | Framing | 1 | 10-08-2009 05:34 PM |
| Thermal Design insulation method | bobwires | Insulation | 2 | 08-10-2009 11:29 PM |
| What is the proper method of Advertising? | Jmfocus | Marketing & Sales | 9 | 07-04-2009 01:07 PM |
| Stick method or Estimating software | rbsremodeling | Business | 21 | 03-11-2009 11:17 AM |
| 3-4-5 Method of Squaring | renkom | Framing | 19 | 12-05-2008 02:07 AM |
| Go to Page... |