How Many Guys You Need To Start A Framing Or Finish Carpenter Crew
I am a building construction student at my local techincal college, I am two more semesters left from getting my degree in building construction technology. But I am wondering how many guys you need to start a carpenter crew? Would myself and two other guys will be enough?
|
|
|
|
|
|
#2 |
|
Thom
Trade: General Contractor/Homebuilder
Join Date: Nov 2006
Location: Albuquerque NM
Posts: 3,197
|
Re: How Many Guys You Need To Start A Framing Or Finish Carpenter Crew
You can frame houses with a three man crew, depending on the house. Some houses take more than three men to lift some of the stuff. Three guys who know what they're doing can get-r-done.
Trim can also be done with three men. Trim can be done with one guy if need by. It all depends on the level and amount of trim. |
|
|
|
|
|
#3 |
|
Pro
Trade: LI,NY designer, new homes, renovation work, concre
Join Date: Mar 2008
Location: Long Island, NY
Posts: 5,426
|
Re: How Many Guys You Need To Start A Framing Or Finish Carpenter Crew
one good carpenter who is used to working alone can get alot of work done, i worked alone for many years, you become very resourceful and creative, a two person team can handle just about any trim work, including cabinetry. light framing can also be accomplished with a two man crew. myself and two good men could frame or build just about anything.
__________________
|
|
|
|
|
|
#4 |
|
Curmudgeon
Trade: carpentry/remodeling/"Yes M'am we do"
Join Date: Apr 2006
Location: Beech Grove, Indiana, Birthplace of the "King of Cool"
Posts: 11,707
|
Re: How Many Guys You Need To Start A Framing Or Finish Carpenter Crew
Two framers, a cut man, and a laborer
is the ideal crew. You're young, you don't need a laborer.
__________________
Put your location in your profile! (Sorry....it seems there really are dumb questions) |
|
|
|
|
|
#5 |
|
DavidC
Trade: Remodeler
Join Date: Feb 2008
Location: NNY
Posts: 1,917
|
Re: How Many Guys You Need To Start A Framing Or Finish Carpenter Crew
Just remember that 1 guy can do alot, 2 guys will not do twice that, the third guys adds even less production. No matter what the task (except heavy lifting) the 4th guy is in the way.
Good Luck Dave
__________________
www.CookContractingLLC.com |
|
|
|
|
|
#6 |
|
Restoration Crazy
|
Re: How Many Guys You Need To Start A Framing Or Finish Carpenter Crew
I'd say three is the minimum to get it done in a reasonable amount of time.
The job schedule usually dictates how many guys you need to get it done in time.
__________________
Jason E Whipple, General Manager Historic House Restoration, Cincinnati, Ohio Facebook | Twitter |
|
|
|
|
|
#7 |
|
Restoration Crazy
|
Re: How Many Guys You Need To Start A Framing Or Finish Carpenter Crew
I agree; after three you need to add in pairs.
__________________
Jason E Whipple, General Manager Historic House Restoration, Cincinnati, Ohio Facebook | Twitter |
|
|
|
|
|
#8 | |
|
The Duke
Trade: Cabinet Maker
Join Date: Mar 2006
Location: Portland, Maine
Posts: 10,105
|
Re: How Many Guys You Need To Start A Framing Or Finish Carpenter CrewQuote:
Most builders get PO'd if you have less than 3, but then it depends what you're building and who you're building for. Most builders want it done now, some will wait for quality.
__________________
If you correct your mind, the rest of your life will fall into place ~Lao Tzu Custom Cabinetry - Portland, Cape Elizabeth, Scarborough, Kennebunkport, Yarmouth, Falmouth, Cumberland, Ogunquit, Maine Salmon Falls Cabinetry |
|
|
|
|
|
|
#9 |
|
Pro
Trade: Carpentry / Fencing / Decks
Join Date: Oct 2007
Location: Savannah, Ga
Posts: 1,216
|
Re: How Many Guys You Need To Start A Framing Or Finish Carpenter Crew
I framed for years with three permanent guys, including myself and I hired an additional helper to come and go when I needed. I built everything from spec homes up to 7000sq customs.
Last edited by curapa; 08-22-2008 at 10:19 PM. |
|
|
|
|
|
#10 |
|
Plumber / Carpenter
|
Re: How Many Guys You Need To Start A Framing Or Finish Carpenter Crew
3 good carpenters can go a long way. They know what the other is doing and can anticipate their every move and be ready for them. Too many laborers not good.
|
|
|
|
|
|
#11 |
|
Pro
Trade: Carpenter & Woodworker
Join Date: Aug 2007
Location: Montgomery, Alabama
Posts: 632
|
Re: How Many Guys You Need To Start A Framing Or Finish Carpenter Crew
Thanks guys for the comments.
|
|
|
|
|
|
#12 |
|
Pro
Trade: Kitchen & Bath
Join Date: Nov 2007
Location: Millersville, PA
Posts: 1,328
|
Re: How Many Guys You Need To Start A Framing Or Finish Carpenter Crew
Trim and framing are definitely two different things, I've done a lot of trim carpentry and cabinet intallations solo. I would say 2 man crew for trim. Kitchens can be tricky with 1 person but I can't imagine how to keep the second busy 100% on a kitchen.
|
|
|
|
|
|
#13 |
|
Pro
Trade: carpenter
Join Date: Dec 2007
Location: Calgary Ab Canada
Posts: 1,728
|
Re: How Many Guys You Need To Start A Framing Or Finish Carpenter Crew
2 man crew for us. It depends on how fast it has to get done.
|
|
|
|
|
|
#14 |
|
General Contractor
Trade: Construction Management
Join Date: Aug 2008
Posts: 684
|
Re: How Many Guys You Need To Start A Framing Or Finish Carpenter Crew
what always facinated me about framing a $2,000,000 home was that the framer recieved $69,000 to build the damn thing
__________________
DECOSnowRemoval&IceControl Serving Delaware County & Philadelphia Pa 610 457-9721 |
|
|
|
|
|
#15 |
|
Registered User
Trade: Framing
Join Date: Aug 2008
Location: Massachusetts
Posts: 3
|
Re: How Many Guys You Need To Start A Framing Or Finish Carpenter Crew
The company I work has 6 workers most of the time (depends on whether my boss feels like working or not). One cutter, one laborer, and 4 guys building. That is a good sized crew and is usually enough manpower to lift any size wall. With 3 workers, as previously stated lifting large gables/walls/beams could be a little tough. But there are usually guys around the jobsite. Just ask for a little help. We have never had a problem getting a few extra hands when we need it. Also plan accordingly--If you know you will be lifting a wall that will need extra men to lift in two hours, make the phone calls now to get help there when you need it so you don't slow progress while waiting to lift the wall. I would say 3 guys is gonna be enough most of the time.
|
|
|
|
|
|
#16 |
|
Pro
Trade: Licensed Home Improvement Contractor
Join Date: Dec 2006
Location: Columbus Ohio
Posts: 272
|
Re: How Many Guys You Need To Start A Framing Or Finish Carpenter Crew
I agree with framerman. When i used to frame the builder required minimum of 4 guys. We had 10 working days to complete large 2000-3300sq ft homes. Thats clean. With a punchlist of 30 items or less.
|
|
|
|
|
|
#17 |
|
A big wannabe
Trade: Framing, decks, trim, Remodels, ground up.
Join Date: Feb 2008
Posts: 147
|
Re: How Many Guys You Need To Start A Framing Or Finish Carpenter Crew
We seem to do best with 7. Two teams of two (4 framers), one cutman, one laborer, and myself to layout, dictate, and float around where needed.
With the cut man also being my "lead guy" (who is also a retired structual engineer who happens to love carpentry and manual labor....) progress keeps flowing when I need to run errands, attend meetings, or line up/plate the next job........ or take the bike up to the track!!! |
|
|
|
|
|
#18 |
|
Marc
Trade: Framing High End Homes / Custom Home Builder
Join Date: Sep 2008
Location: Greenville South Carolina
Posts: 3
|
Re: How Many Guys You Need To Start A Framing Or Finish Carpenter Crew
When you start you have to do the best you can with what you have in hand.
My first house was only 3000 sqft(17 years ago) Me and my partner built it ourselves. Dont hire unless you can aford it. |
|
|
|
|
|
#19 |
|
Member
Trade: General
Join Date: Sep 2008
Location: Livermore CA.
Posts: 90
|
Re: How Many Guys You Need To Start A Framing Or Finish Carpenter Crew
When I started it was myself and 2 walljacks framing 1,500 to 1,700 sq. ft. homes. Now, myself as cut man/layout 2 carpenters and a laborer willing to learn.
Last edited by nailman; 09-16-2008 at 08:32 PM. |
|
|
|
![]() |
| Thread Tools | Search this Thread |
| Display Modes | Rate This Thread |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Quality Finish Carpenter available in LA CA area | woodtradesman | Help Wanted or Looking For Work | 3 | 04-23-2008 01:12 PM |
| Framing crew sizes? | baracus | Carpentry | 10 | 01-29-2008 08:23 PM |
| Platform Framing | UKframer | Framing | 5 | 12-23-2007 12:45 PM |
| Any Generals looking to sub to framing Crew? | motivationman75 | Help Wanted or Looking For Work | 1 | 10-31-2005 11:01 PM |
| Framing Crew Going to Wildwood N.J. | strat | Help Wanted or Looking For Work | 1 | 09-04-2005 12:00 AM |
| Go to Page... |