Generally Speaking - How Much Do You Mark Up A Sub/material?

 
Thread Tools Search this Thread Display Modes
Old 02-17-2009, 02:27 AM   #1
New General Contractor
 
Titodbuilder's Avatar
 
Trade: General Contractor
Join Date: Feb 2009
Location: DC Area - Northern VA
Posts: 88

Generally Speaking - How Much Do You Mark Up A Sub/material?


Is there a rule of thumb as to how much one should mark up a sub's job? How about material?

Thank you.

Titodbuilder is offline  
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Old 02-17-2009, 02:32 AM   #2
I builds'em
 
Winchester's Avatar
 
Trade: Renovations & Decks
Join Date: Jun 2008
Location: Vancouver, BC, Canada
Posts: 3,522

Re: Generally Speaking - How Much Do You Mark Up A Sub/material?


Quote:
Originally Posted by Titodbuilder View Post
Is there a rule of thumb as to how much one should mark up a sub's job? How about material?

Thank you.
No rules for any fingers.
Winchester is offline  
Old 02-17-2009, 07:12 AM   #3
Pompass Ass
 
bwalley's Avatar
 
Trade: Certified Building and Certified A/C Contractor
Join Date: Jan 2009
Location: Plant City, Florida
Posts: 2,090

Re: Generally Speaking - How Much Do You Mark Up A Sub/material?


Quote:
Originally Posted by Titodbuilder View Post
Is there a rule of thumb as to how much one should mark up a sub's job? How about material?

Thank you.
100-200%, whatever the market will bear.
bwalley is offline  
Old 02-17-2009, 07:34 AM   #4
You did what??
 
J F's Avatar
 
Trade: Carpenter
Join Date: Dec 2005
Location: North of Atlanta
Posts: 6,601

Re: Generally Speaking - How Much Do You Mark Up A Sub/material?


We usually just charge half of what the sub charges us, but we make it up on volume.
J F is offline  
Old 02-17-2009, 08:18 AM   #5
Pro
 
NAV's Avatar
 
Trade: commercial building restoration
Join Date: Sep 2008
Location: Cleveland
Posts: 381

Re: Generally Speaking - How Much Do You Mark Up A Sub/material?


Don't ask bwalley how to markup - he has a little trouble in the math department.
NAV is offline  
Old 02-17-2009, 08:21 AM   #6
Pro
 
SDC's Avatar
 
Trade: Remodeling
Join Date: Jan 2009
Location: New Hampshire
Posts: 295

Re: Generally Speaking - How Much Do You Mark Up A Sub/material?


Quote:
Originally Posted by J F View Post
We usually just charge half of what the sub charges us, but we make it up on volume.


I agree, do twice as much work, for half the $ and come out even
__________________
David Cookman
SDC is offline  
Old 02-17-2009, 12:24 PM   #7
New General Contractor
 
Titodbuilder's Avatar
 
Trade: General Contractor
Join Date: Feb 2009
Location: DC Area - Northern VA
Posts: 88

Re: Generally Speaking - How Much Do You Mark Up A Sub/material?


I understand about having fun and having a good sense of humor and will I will be the first to laught at something, but do you guys have anything to say on the subject aside from the 1st grade humor? I'll even take and maybe even snicker at some of the post if there is a morsel of reality inserted be tween the yuk-yuks.

I'll just assume it is the way I posted as many have been very helpful with other questions in this very forum.

Cheers
Titodbuilder is offline  
Old 02-17-2009, 12:32 PM   #8
Professional Instigator
 
rbsremodeling's Avatar
 
Trade: Design Build Remodeling Contractor DC MD
Join Date: Nov 2007
Location: Washington, DC/ Maryland
Posts: 6,872

Re: Generally Speaking - How Much Do You Mark Up A Sub/material?


Quote:
Originally Posted by Titodbuilder View Post
I understand about having fun and having a good sense of humor and will I will be the first to laught at something, but do you guys have anything to say on the subject aside from the 1st grade humor? I'll even take and maybe even snicker at some of the post if there is a morsel of reality inserted be tween the yuk-yuks.

I'll just assume it is the way I posted as many have been very helpful with other questions in this very forum.

Cheers
There is no rule of thumb. It varies from contractor to contractor based on your overhead and salary requirements etc.

You basically were given the answer in the last thread. What has changed since then? you listed your overhead and salary requirements.

So multiply your job by that markup number according to the amount of jobs you have going on and the length of the projec

Thats it, no mystery. You adjust the markup as you gain more experience on how the job, employees and customers react.
__________________

rbsremodeling is offline  
Old 02-17-2009, 12:34 PM   #9
Pompass Ass
 
bwalley's Avatar
 
Trade: Certified Building and Certified A/C Contractor
Join Date: Jan 2009
Location: Plant City, Florida
Posts: 2,090

Re: Generally Speaking - How Much Do You Mark Up A Sub/material?


Quote:
Originally Posted by NAV View Post
Don't ask bwalley how to markup - he has a little trouble in the math department.

You are the moron who can't do basic math.
bwalley is offline  
Old 02-17-2009, 12:36 PM   #10
egotistical prick
 
Cdat's Avatar
 
Trade: Wood Inlay
Join Date: Apr 2007
Location: Swartz Creek, Michigan
Posts: 2,633

Re: Generally Speaking - How Much Do You Mark Up A Sub/material?


Depends on cost and time. A medallion I make I'll start rate at 1200 dollars and go up from there. Materials? Usually under 100 bucks. Time? Depends on if it is scrolled, laser or cut another way. Time to install? 2 hours max. It is whatever your customers are willing to pay.

Market dictates.
Cdat is offline  
Old 02-17-2009, 12:38 PM   #11
You did what??
 
J F's Avatar
 
Trade: Carpenter
Join Date: Dec 2005
Location: North of Atlanta
Posts: 6,601

Re: Generally Speaking - How Much Do You Mark Up A Sub/material?


If 1 person each says: 0% 10% 30% 50% 67%....what can you take away from that?

It's going to be all over the board depending on a LOT of different factors....add to that that a lot of us don't like "dropping our drawers" in a public forum, as well as how many times it gets asked, ....well, you get the idea...a lot of "comedy" ensues...
J F is offline  
Old 02-17-2009, 12:59 PM   #12
Pro
 
dubz's Avatar
 
Trade: General Contracting
Join Date: Sep 2008
Location: Northwest Hills of CT
Posts: 290

Re: Generally Speaking - How Much Do You Mark Up A Sub/material?


I'm pretty sure around here it's listed as 15%, and the hourly rate on the carpentry end is the thing that is adjusted. The guys who can sell, get the bigger jobs and have bigger overhead are able to get a higher rate obviously.
dubz is offline  
Old 02-17-2009, 01:00 PM   #13
Pro
 
dubz's Avatar
 
Trade: General Contracting
Join Date: Sep 2008
Location: Northwest Hills of CT
Posts: 290

Re: Generally Speaking - How Much Do You Mark Up A Sub/material?


I make like tree-fiddy
dubz is offline  
Old 02-17-2009, 01:20 PM   #14
New General Contractor
 
Titodbuilder's Avatar
 
Trade: General Contractor
Join Date: Feb 2009
Location: DC Area - Northern VA
Posts: 88

Re: Generally Speaking - How Much Do You Mark Up A Sub/material?


Thanks RBS, I know the answer and can do the math. I thought there might be something I am missing because when I ran my latest bid by my lead foreman he authoritatively told me I was too high, and again authoritatively spewed out some percentages associated with work that was subbed out and informed me that I was too high on my bid. I went back and checked my numbers and I had not missed anything apparent major. So, I though about the fact he seemed to know some general percentages and perhaps I was missing something. I have no field experience; hence, my question on this thread.

It sounds like he was full of it and I should go with what makes business sense not what he so authoritatively says is the "industry norm" that sounds like it does not exist.

Follow up question: Are subbed quotes treated the same as labor and material for calculation purposes? In other words, if I sub a large part of a project (say a large patio) do I still calculate the cost of that section as if it were my time and labor and apply the same overhead costs as the work performed by employees with our material?
Titodbuilder is offline  
Old 02-17-2009, 01:26 PM   #15
New General Contractor
 
Titodbuilder's Avatar
 
Trade: General Contractor
Join Date: Feb 2009
Location: DC Area - Northern VA
Posts: 88

Re: Generally Speaking - How Much Do You Mark Up A Sub/material?


BTW - I am sorry for asking silly questions guys. I belong to one other forum having to do with travel and I know what you mean. I think I am asking the equivalent to "Is there a ferry to Cuba" question, where everyone piles on and has fun with it. There is a lot of stuff in old posts here and I have started going through them...bear wioth me and the stupid questions will stop soon.

Cheers
Titodbuilder is offline  
Old 02-17-2009, 04:09 PM   #16
I builds'em
 
Winchester's Avatar
 
Trade: Renovations & Decks
Join Date: Jun 2008
Location: Vancouver, BC, Canada
Posts: 3,522

Re: Generally Speaking - How Much Do You Mark Up A Sub/material?


Quote:
Originally Posted by Titodbuilder View Post
Follow up question: Are subbed quotes treated the same as labor and material for calculation purposes? In other words, if I sub a large part of a project (say a large patio) do I still calculate the cost of that section as if it were my time and labor and apply the same overhead costs as the work performed by employees with our material?
If you are subbing out jobs they should supply their own materials and have their own employees. Why would you act as if they weren't?
Winchester is offline  
Old 02-17-2009, 06:20 PM   #17
New General Contractor
 
Titodbuilder's Avatar
 
Trade: General Contractor
Join Date: Feb 2009
Location: DC Area - Northern VA
Posts: 88

Re: Generally Speaking - How Much Do You Mark Up A Sub/material?


I understand they are supplying everything, so how would I assign markup/profit and overhead when it comes to my overall sales price for that particular part of the job? If I count the sub's price as labor and material and assign the overall overhead and profit then the selling price for this part becomes too high. I think my dumb ass is complicating this too much, but......
Titodbuilder is offline  
Old 02-17-2009, 06:23 PM   #18
Professional Instigator
 
rbsremodeling's Avatar
 
Trade: Design Build Remodeling Contractor DC MD
Join Date: Nov 2007
Location: Washington, DC/ Maryland
Posts: 6,872

Re: Generally Speaking - How Much Do You Mark Up A Sub/material?


Quote:
Originally Posted by Titodbuilder View Post
I understand they are supplying everything, so how would I assign markup/profit and overhead when it comes to my overall sales price for that particular part of the job? If I count the sub's price as labor and material and assign the overall overhead and profit then the selling price for this part becomes too high. I think my dumb ass is complicating this too much, but......
You mark it up as you would any other cost. You have your overhead.

Sub cost are the same as labor and material costs to me. I just add my markup as across the board.
__________________

rbsremodeling is offline  
Old 02-17-2009, 08:45 PM   #19
I builds'em
 
Winchester's Avatar
 
Trade: Renovations & Decks
Join Date: Jun 2008
Location: Vancouver, BC, Canada
Posts: 3,522

Re: Generally Speaking - How Much Do You Mark Up A Sub/material?


I calculate my mark-up and overhead mostly in my labour. Materials and subs mark-up are like a bonus. Actually, they usually make up for me miscalculating or underestimating something.
Winchester is offline  
Old 02-17-2009, 09:26 PM   #20
Structural Engineer
 
Aggie67's Avatar
 
Trade: Mechanical, Structural
Join Date: Aug 2008
Location: New Jersey
Posts: 513

Re: Generally Speaking - How Much Do You Mark Up A Sub/material?


Quote:
Originally Posted by rbsremodeling View Post
Sub cost are the same as labor and material costs to me. I just add my markup as across the board.
Amen.
Aggie67 is offline  


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Average Mark Up galanbro Drywall 23 06-05-2010 10:01 AM
Comparison of Van Mark I & II brakes windowjim Windows, Siding and Doors 10 02-02-2009 07:41 AM
How does everybody handle the mark up issue? ottagosoon Marketing & Sales 26 01-21-2009 10:24 PM
How much do you mark up materials?? Nail banger Business 3 12-30-2008 04:50 PM
Mark Out Responsibility Aggie67 Excavation & Site Work 16 11-13-2008 06:25 AM

Join Now... It's Fast and FREE!

Privacy Badge
I am a professional contractor
I am a DIY Homeowner
ContractorTalk.com is for
PROFESSIONAL CONTRACTORS ONLY!

At ContractorTalk.com we cater exlusivly to professional contractors who make their living as a contractor. Knowing that many homeowners and DIYers are looking for a community to call home, we've created www.DIYChatroom.com DIY Chatroom is full of helpful advices and perfect for DIY homeowners.

Redirecing in 10 seconds
No Thanks
terms of service

Already Have an Account?