Dirt Work

 
Thread Tools Search this Thread Display Modes
Old 01-19-2006, 02:38 AM   #1
Registered User
 
Blackdog's Avatar
 
Trade: excavation
Join Date: Jan 2006
Posts: 2
Question

Dirt Work


I've started doing residential dirt work several years ago but have always worked in inches while using the grade stake. However, I would like to bid some commercial work which is all in tenths. I'm looking for some information on how to convert....... If the plan says finish grade is 4147.50 are all the numbers to the left of th decimal in feet, to right of the decimal in inches and thousands of inches................

Blackdog is offline  
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Old 01-19-2006, 08:39 AM   #2
Pro
 
PipeGuy's Avatar
 
Trade: underground
Join Date: Oct 2004
Location: Southeast USA
Posts: 3,228

Re: Dirt Work


No need to double post dude. Someone will get to it.
PipeGuy is offline  
Old 01-19-2006, 10:19 AM   #3
Pro
 
Peladu's Avatar
 
Trade: General Contractor
Join Date: Jan 2006
Location: Chicago
Posts: 1,370

Re: Dirt Work


For a second I was wondering where my reply went....
Peladu is offline  
Old 11-10-2009, 08:57 PM   #4
Zimmermann
 
BrianFox's Avatar
 
Trade: Wood Cutter
Join Date: Apr 2009
Location: Philadelphia
Posts: 328

Re: Dirt Work


Please dont solicit here....
__________________
Happiness is produced not so much by great pieces of good fortune that seldom happen, as by little advantages that occur every day.
- Benjamin Franklin
BrianFox is offline  
Old 11-10-2009, 09:23 PM   #5
Gumby
 
IanS's Avatar
 
Trade: Concrete
Join Date: Sep 2009
Location: NW Florida Panhandle
Posts: 112

Re: Dirt Work


Tech Tim has you covered. But you don't need software to figure dirt.
Lx Wx D x(weight of 1 cubic ft of compacted material) divided by 2000 equals tons. Most large rock is 90lbs Most blended gravels are 120-130lbs and asphalt is 130-140lbs depending on the rock used. You can ask your quarry, consult a book, engineer, or build a 1 cubic foot box and pack it and weigh it yourself. Math for triangles ie slopes I assume you know. On small jobs add 10 %. On Mid jobs add 5% on Huge jobs add 3%. Its all in the measurements though.

Example 100 ft lot by 25' to road, 4" deep approx. Brown dirt

((100 x 25 x .333 x 120)/ 2000 ) times 1.05 = 52.5 tons.

In yards (100 x 25 x .333)/27 times 1.05= 32-33 yards

Canadians adjust tonnes accordingly, and I apologise if you knew your math already.

KGMZ below has a way better plan with the 10ths rod or scale below.

Last edited by IanS; 11-10-2009 at 10:55 PM. Reason: Better
IanS is offline  
Old 11-10-2009, 10:42 PM   #6
Pro
 
Kgmz's Avatar
 
Trade: General, Electrical, and Plumbing Contractor
Join Date: Feb 2007
Location: Portland, OR & Eatonville, WA
Posts: 1,264

Re: Dirt Work


1 tenth of a foot, .10 is 1.2 inches.

But why do you want to convert?

How are you measuring and what are you measuring?

Are you using a laser to check grade, depth of pipe, etc. It's much easier to stay with the engineers scale on the plans than to convert back and forth. Too much chance of mistakes being made.

If using a laser is your rod in inches or tenths, if using a optical level are you using a rod or tape measure and is it in inches or tenths. Whatever you are using buy a rod or tape measure in tenths. Go to your local surveyers supply and you can get a 25' tape in tenths for under $10. A rod will cost more, about $50 for a inexpensive aluminum rod, but is well worth cost to minimize mistakes.
Kgmz is offline  
Old 11-11-2009, 12:35 AM   #7
Pro
 
cexcavation's Avatar
 
Trade: Excavation Contractor
Join Date: Apr 2008
Posts: 374

Re: Dirt Work


To convert, take the decimal and multiply by 12.

Example 1.8' is right at 1' 9 and 5/8".

The decimal represents % of a foot. The whole number is simply feet. All you need to convert is the decimal portion, so .8 * 12 =9.6"

Once you have converted to feet, the decimal now represents % of an inch which you can do in your head knowing that 5/8" is .625.

Now that you are totally confused, go out and buy the tape measure and rod the KGMZ was referring to!!!!
cexcavation is offline  
Old 11-11-2009, 08:57 PM   #8
superdave111a
 
superdave111a's Avatar
 
Trade: general contractor
Join Date: Sep 2009
Location: pasadena md.
Posts: 5

Re: Dirt Work


something else you need to be aware of is basically all engineers will use some random mesurement as a benchmark such as setting the finished floor elevation at 100'.0'' so you may need to take shots from this at some point. although the stake out should give you all your cuts and fills, that is if you can keep everyone from running them over.
superdave111a is offline  
Old 11-11-2009, 09:11 PM   #9
Pro
 
NJ Brickie's Avatar
 
Trade: Bricklayer
Join Date: Jan 2009
Location: South Jersey
Posts: 557

Re: Dirt Work


Quote:
Originally Posted by superdave111a View Post
something else you need to be aware of is basically all engineers will use some random mesurement as a benchmark such as setting the finished floor elevation at 100'.0'' so you may need to take shots from this at some point. although the stake out should give you all your cuts and fills, that is if you can keep everyone from running them over.

Random measurement? Every job that I can think of right now that I've done the bench mark number is elevation above sea level. No guess work involved.
NJ Brickie is offline  
Old 11-11-2009, 11:00 PM   #10
Earthwork Calcualtions!
 
TechTim's Avatar
 
Trade: Earthwork, Sitework
Join Date: Oct 2009
Posts: 11

Re: Dirt Work


Hmmmm.. ok, my post is gone. I guess someone has something against me plugging myself.... really? I know we are going communist and all, but I "thought" we where still a capitalist nation (for now).

I tried to help ya Blackdog, I guess someone had a problem with that... sorry dude.

Good Luck with your earthwork endeavors!
Tim
TechTim is offline  
Old 11-11-2009, 11:33 PM   #11
Maker of fine kindling
 
Gus Dering's Avatar
 
Trade: cabinet maker
Join Date: Oct 2008
Location: Santa Rosa CA
Posts: 4,753
Send a message via Yahoo to Gus Dering

Re: Dirt Work


Quote:
Originally Posted by TechTim View Post
Hmmmm.. ok, my post is gone. I guess someone has something against me plugging myself.... really? I know we are going communist and all, but I "thought" we where still a capitalist nation (for now).

I tried to help ya Blackdog, I guess someone had a problem with that... sorry dude.

Good Luck with your earthwork endeavors!
Tim
Although I was not the mod that trashed your post, I considered it.

You have to understand we get a ton of low post members coming here to push what ever widget they are pedaling.

Yours may not have been that but it was close enough to get tossed. If you want to sell your software to someone you see that may benefit from it, send them a PM and make your offer.

Hang out longer and contribute, let more people get to know you and things like this will probably be overlooked because we know what your true intentions are.

Don't get your panties all wadded up. The mods are doing the best we can to keep this place what it is supposed to be. A spam free place to talk with other pros.

OK?
__________________
Every parent who has walked barefoot into their child's room late at night hates Legos
Gus Dering is offline  
Old 11-12-2009, 11:43 PM   #12
Pro
 
tommytwo's Avatar
 
Trade: Remodeling and Home Performance
Join Date: Mar 2009
Location: MN
Posts: 119

Re: Dirt Work


Besides, I'm sure blackdog either figured it out or gave up by now.
tommytwo is offline  
Old 11-13-2009, 11:54 AM   #13
Curmudgeon
 
neolitic's Avatar
 
Trade: carpentry/remodeling/"Yes M'am we do"
Join Date: Apr 2006
Location: Beech Grove, Indiana, Birthplace of the "King of Cool"
Posts: 11,707

Re: Dirt Work


From an old dirt guy.
(since no one posted it)
.08' = 1"
.17' = 2"
.25' = 3"
.33' = 4"
.42' = 5"
.50' = 6"
.58' = 7"
.67' = 8"
.75' = 9"
.83' = 10"
.92' = 11"

Not 100%, but close enough for dirt
and commonly accepted conversions.
__________________
Put your location in your profile!
(Sorry....it seems there really are dumb questions)
neolitic is offline  
Old 11-13-2009, 04:37 PM   #14
Earthwork Calcualtions!
 
TechTim's Avatar
 
Trade: Earthwork, Sitework
Join Date: Oct 2009
Posts: 11

Re: Dirt Work


Gus Dering - Fair Enough
TechTim is offline  
Old 11-13-2009, 07:16 PM   #15
Maker of fine kindling
 
Gus Dering's Avatar
 
Trade: cabinet maker
Join Date: Oct 2008
Location: Santa Rosa CA
Posts: 4,753
Send a message via Yahoo to Gus Dering

Re: Dirt Work


Quote:
Originally Posted by TechTim View Post
Gus Dering - Fair Enough
Thanks for the response.

You seem like a guy with things to contribute here. I hope you find it fun to be here.
__________________
Every parent who has walked barefoot into their child's room late at night hates Legos
Gus Dering is offline  
Old 11-16-2009, 04:01 PM   #16
Member
 
Destin Handyman's Avatar
 
Trade: Handyman/Pressure Washing/Painting
Join Date: Nov 2009
Location: Destin, Fl
Posts: 38

Re: Dirt Work


!!!!!!!!!!
Destin Handyman is offline  
Old 11-16-2009, 04:49 PM   #17
Pro
 
BuiltByMAC's Avatar
 
Trade: Construction
Join Date: Mar 2006
Location: Eugene, OR
Posts: 3,019

Re: Dirt Work


Tim, you might want to spell check your User Title under your avatar...

Mac
BuiltByMAC is offline  
Old 11-16-2009, 05:49 PM   #18
Contractor
 
tgeb's Avatar
 
Trade: Excavation, Foundation, Concrete
Join Date: Feb 2006
Location: Maryland
Posts: 3,271

Re: Dirt Work


Quote:
Originally Posted by BuiltByMAC View Post
Tim, you might want to spell check your User Title under your avatar...

Mac
__________________
Tom

www.gebcon.com
tgeb is offline  


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to Pay Piece Meal and Sleep at Night dirt diggler Business 34 03-13-2011 10:54 AM
Side Work specwood Business 81 05-12-2009 07:19 AM
Looking for remodel or new construction work MDShinn Help Wanted or Looking For Work 0 02-13-2007 10:06 AM
Why I work only for Contractors. Debookkeeper Off Topic (Non Trade) 10 09-19-2006 10:03 PM
On discouraging DIY electrical work... mdshunk Electrical 52 02-18-2006 12:58 AM

Join Now... It's Fast and FREE!

Privacy Badge
I am a professional contractor
I am a DIY Homeowner
ContractorTalk.com is for
PROFESSIONAL CONTRACTORS ONLY!

At ContractorTalk.com we cater exlusivly to professional contractors who make their living as a contractor. Knowing that many homeowners and DIYers are looking for a community to call home, we've created www.DIYChatroom.com DIY Chatroom is full of helpful advices and perfect for DIY homeowners.

Redirecing in 10 seconds
No Thanks
terms of service

Already Have an Account?