Need Help : How to bill for a cost plus project without leaving out any indirect cost, thank you.
|
|
|
|
|
|
#2 | |
|
Sweeper of fine saw dust
Trade: Project Manager by day, Cabinet maker for fun
Join Date: Feb 2008
Location: Delaware
Posts: 1,033
|
Re: Cost PlusQuote:
we have a job as cost plus. we bill our costs plus 12%. so we have to have invoices from our subs and for materials. we invoice for anytime that we spend on the site as well. then we add that and add 12% to the total for O&P. materials also include dumpsters, porta pots, electric bills, signs, everything. all of the gen conditions go on the materials purchased invoice Last edited by chris klee; 06-10-2008 at 09:22 PM. |
|
|
|
|
![]() |
| Thread Tools | Search this Thread |
| Display Modes | Rate This Thread |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| The cost of a breach | KentWhitten | Off Topic (Non Trade) | 2 | 03-26-2008 06:42 PM |
| Rise in the cost to live. | Floordude | General Discussion | 2 | 03-22-2008 07:26 PM |
| employee cost | Travis | Roofing | 10 | 12-30-2006 07:25 PM |
| Permit cost/ how much? | dougchips | General Discussion | 14 | 10-29-2006 10:06 AM |
| Go to Page... |