01-24-2007, 11:46 AM
|
#1
|
|
Registered User
Trade:
Builder
Join Date: Sep 2006
Posts: 6
|
Help Installing Hardwood over old/new Concrete Slab
Hi,
I am building a 2-story home for the first time and the first floor is a mix of
old
and new concrete slab thanks to the expansion of the original floorplan.
Basically I
tore it down to slab, added the new areas and reinforcement footings.
So I spoke to one flooring guy about how he would approach the hardwood floor
install:
1. 2 sheets of 3/8" plywood
2. Vapor barrier paper
3. Oak Hardwood
4. Finished floor from slab is 1.5"
He said maybe some concrete leveling. I wasn't so convinced he knew what he was
doing. Sounds reasonable?
I was thinking that at least to check the slab straightness was to:
1. 6 foot level to find high-low spots
2. Correct with a concrete leveling such as Ardex K-15
How would you check and prep for hardwood over slab and what underlayments would
you
use? I live in the San Francisco area so we don't get frost or any extreme
climate
temps.
Thanks for your help!
|
|
|
Warning: The topics covered on this site include activities in which there exists the potential for serious injury
or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!
Join the #1 Contractor Forum Today - It's Totally Free!
ContractorTalk.com - Are you a Professional Contractor? If so we invite you to join our community and see what it has to offer. Our site is specifically designed for you and it's the leading place for contractors to meet online. No homeowners asking DIY questions. Just fellow tradesmen who enjoy talking about their business, their trade, and anything else that comes up. No matter what your trade is you'll find that ContractorTalk.com is a great community to join. Best of all it's totally free!
Join ContractorTalk.com - Click Here

|
01-24-2007, 06:24 PM
|
#2
|
|
Pro
Trade:
general contractor - SFR
Join Date: Aug 2005
Location: north georgia
Posts: 117
|
I try to talk my customers out of solid hardwood flooring below grade. You might try engineered wood. You can then still call it a "wood floor" and you honestly can't see the difference. If you go solid wood however, I've had good luck with this method:
a. level floor
1. seal concrete
2. lay down 6 mil poly vapor barrier. overlap and tape joints.
3. fur out floor 12" o.c. with pressure treated 1x material, around
perimeter, too. be sure concrete nails are slightly countersunk
for shrinkage of the p.t. wood.
4. add 1 layer typical wood subflooring (3/4" advantech, etc.)
be sure nails aren't too long to hit the concrete or angle them.
5. nail down floor as you would on a regular wood sub-floor, considering
the furring strips as your "joists"
Last edited by georgia dawg; 01-24-2007 at 06:36 PM.
|
|
|
01-24-2007, 11:00 PM
|
#3
|
|
Pro
Trade:
Residential Contractor
Join Date: Feb 2004
Location: Jensen Beach, FL
Posts: 10,376
|
You definitely don't want wood between the slab and vapor barrier.
__________________
You can't solve you're problems with the same level of thinking that created the problems.
Albert Einstein
|
|
|
01-25-2007, 01:45 AM
|
#4
|
|
Registered User
Trade:
Builder
Join Date: Sep 2006
Posts: 6
|
Quote:
Originally Posted by Teetorbilt
You definitely don't want wood between the slab and vapor barrier. 
|
Teetorbilt,
Question on why not a vapor barrier between the concrete and the wood? Where else could it go between the subfloor ply and the concrete surface?
I like the idea of sealing the concrete as an added measure, but furring for the subfloor?? 1.5" from concrete to finished wood surface seems plenty high already and adding a furring layer would be a bit much, I would imagine.
BTW, this is not below grade. And landscape will be properly graded to keep the drainage away from the foundation as much as is possible.
Thanks for your opinions!
|
|
|
01-25-2007, 05:46 PM
|
#5
|
|
Pro
Trade:
general contractor - SFR
Join Date: Aug 2005
Location: north georgia
Posts: 117
|
Be sure you have at least 3/4" something or another underneath your 3/4" solid wood or your 2" nails, even at an angle, are going to hit the concrete. Using shorter 1 3/4" nails instead of 2" can help alleviate this issue some. I wouldn't go any shorter, though.
|
|
|
06-03-2008, 08:42 PM
|
#6
|
|
Registered User
Trade:
Remodeling & Buy, Fix, Sell.
Join Date: Jun 2008
Posts: 1
|
Why not 3/4 ply sleepers
I am about to start a remodeling project in south Texas. Many of the older homes in this area that have solid wood over concrete slabs have solid 3/4 sleepers set in tar. I am considering hardwoods for this new project.
Does anyone have feedback on setting 4" strips of treated 3/4 plywood in rivers of tar for the sleepers? I am trying to minimize the height but do not want to use engineered.
|
|
|
06-04-2008, 11:36 AM
|
#7
|
|
Knowledge Factory
Trade:
Certified Floorcovering Failure Investigator
Join Date: Aug 2007
Location: Austin, Texas
Posts: 1,289
|
Screeds in an asphalt bed, work well, as long as the moisture emissions are not sky high.
Not only will the screeds need to be set into ashalt, the entire floor needs to be covered as a complete membrane. Then a minimum of 2 coats over the screeds. Pretty messy, if you ask me.
Pressure treated wood, is going to have a high moisture content. Be very careful, as it can cause cupping.
|
|
|
06-04-2008, 12:02 PM
|
#8
|
|
Pro
Trade:
LI,NY designer, new homes, renovation work, concre
Join Date: Mar 2008
Location: Long Island, NY
Posts: 4,152
|
Quote:
Originally Posted by georgia dawg
I try to talk my customers out of solid hardwood flooring below grade. You might try engineered wood. You can then still call it a "wood floor" and you honestly can't see the difference. If you go solid wood however, I've had good luck with this method:
a. level floor
1. seal concrete
2. lay down 6 mil poly vapor barrier. overlap and tape joints.
3. fur out floor 12" o.c. with pressure treated 1x material, around
perimeter, too. be sure concrete nails are slightly countersunk
for shrinkage of the p.t. wood.
4. add 1 layer typical wood subflooring (3/4" advantech, etc.)
be sure nails aren't too long to hit the concrete or angle them.
5. nail down floor as you would on a regular wood sub-floor, considering
the furring strips as your "joists"
|
this will work well, i have used this approach as well, you can even add 3/4'' rigid foam between the 12'' centers, adds a little insulation.
__________________
|
|
|
| Thread Tools |
Search this Thread |
|
|
|
| Display Modes |
Rate This Thread |
Linear Mode
|
|
Posting Rules
|
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts
HTML code is Off
|
|
|
|
|